.

Thursday, January 24, 2019

Project Management Essay

Table of Contents performance on the thickener mesh plat3Determination of the timing of activities and the total fellate4 The meet cadence and the precise path5 The earlier date the frame kitty be completed disposed the scratch line date Monday 7th may 2012..5 The effect on the date of the whole go for if..5 bodily process F is delayed by adept day5natural process N is delayed by mavin day6Activity O is completed one day beforehand(predicate) ..6 The limitations of Ne dickensrk plots..67 5 12 D 7 0 121. Activity on the node entanglement diagram5 2 7 C 5 0 70 4 4 A 0 0 44 1 5 B 4 0 512 1 13 E 21 9 2212 6 18 F 16 4 2212 8 20 G 14 2 2212 10 22 H 12 0 2222 10 32 I 22 0 3232 4 36 J 32 0 3636 1 37 K 45 9 4636 6 42 L 40 4 4636 10 46 M 36 0 4636 2 38 N 44 8 4646 4 50 O 46 0 5050 1 51 P 50 0 5151 1 52 Q 51 0 52Legend soonest start clock (EST) Duration Earliest hold on era (EFT) lying-in Latest start clipping (LST) Total Float Latest last up cadence (LFT)Critic al Path The look age 52 long timeA, B, C, D, H, I,J,M,O,P,Q2. Determination of the timing of activities and the total floatThe soonest start time (EST), the earliest time at which the node could be reached, and the earliest finish time (EFT), the latest time by which the node must be reached if the project is to finsh by its compulsory completion date, are produced by a forward draw out through the intercommunicate. The first step of the forward pass is calculating the earliest start time, commencing from the unique project start node and finishing at the unique project completion node. The first tax of the project is A, hence the earliest start time of occupation A may be set to zero since no information has been prone as to the starting day of the toil. The next step is determining the EFT, which is cypher by adding the EST to the time of the task. attached the duration of either task, the proces of calculating the EFT of either task is quite straight forward assu ming that the EST of every task is the EFT of the previous task. However, when it comes to a merge application the largest value must be taken.The latest event propagation, refering to the latest start time (LST) and the latest finish time (LFT), are the times when a particular task may commence without delaying the project duration and when the particular task may be completed without delaying the project duration. Usually such times are required when the project has an established target finish date. The latest event times are metric using the backward pass proficiency. Such technique begins by determining the latest finish time of the last task of the project completion and works backwards to the start node. Since no inforamtion has been given regarding the target finish date of the project, the LFT of the project is equal to the EFT in which the project evict be done. Hence, the LST can be calculated by subtracting theduration from the LFT. working(a) backwards, the LST o f the previous task is to be the EFT of the task with the opinionated EST. It is important that when it comes to a merge activity the smallest value must be taken.Once the LFT of every task is completed the total float can be calculated by the following formulaTotal float = latest time of finish event earliest time of start event duration3. The project duration and the sarcastic pathThe project duration was unconquerable by adding the EST of every task to the durtation of every task carried forward from one task to another. Hence, the longest path determines the duration of the project and therefore establishes the critical path since the longest necessary path through a network of activities when respecting their interdependencies is considered to be critical. Furthermore, the critical path may in like manner be intractable as the path with the least float. In fact, the critical path determined above has the least float (0) and the longest duration of the project (52 days).4 . The earliest date the project can be completed given the starting date Monday 7th May 2012The earliest finishing time of the project as established in the diagram is that of fifty two days. Given that the project can be completed using a basketball team day working week, therefore it provide take ten weeks and two days to complete the project. Calculating the weeks and days from the 7th of May 2012, the earliest date in which the project can be completed is on Tuesday 17th July 2012.5. The effect on the duration of the whole project ifa. Activity F is delyaed by one day.The delay in activity F will not affect the duration of the whole project as such because the increase in duration will not devolve the total float of activity F, therefore does not exceed the duration of activity H which forms part of the critical path. Activity F can only affect the duration of the project if it delays by five days as it will surpass the amount of days that the activity is allowed to floa t.b. Activity N is delayed by one dayThe total float of activity N is that of eight days. Therefore, the amount of days that activity N will be delayed does not affect the duration of the project. In this case, in order for the duration of the projet to be effected the delay time of activity N has to be of nine days as it will surpass the duration of activity M which is part of the critical path.c. Activity O is completed one day earlyGiven that the activity forms part of the critcal path, therefore the duration of the project will be touch on not only by being completed early scarce also if the activity had to delay since the total float is that of zero. In this case, since the activity will be carried out one day sooner than expected, the project will be completed one day early and the duration of the project will be that of fifty one days preferably of fifty two days.6. The limitations of Network diagramsIn project managent network diagrams arouse several advantages when it c omes to scheduling projects. One major advantage is that it helps project managers aim the most important activities which may affact the project schedule. However, such diagrams have also limitations to their use in scheduling a project. For large projects a network diagram may not be the ideal scheduling technique because of several activities and dependency relationships that can make the diagram complex to adjudge out and ticklish for other employees to understand.Furthermore, if the envision of the project changes during the completion of the project, the precendence network will have to be done all over again. In addition, such diagram therefore, may be considered as a time consuming technique. The techniuqe may also take too much to aim all activities and inter-relate them to multiple project paths.Network diagrams may also not be suitable for first time projects because if project cannot be scurvy down into distinctive activities with known duratrion for every acti vity then the precendence diagram cannot be drawn. The most critical factor is the duration because on a new project the duration for certain activities may be difficult to estimate, hence the network diagram may be far from actual. other limitation of network diagrams is when a shift of resource occurs. When the network diagram encounters re-allocation of resources such as employees being transfered from one acvtiviy to another, the activity completion time may be changed because of stoppage or other relevant reasons and the plan of the project may be disrupted.A network diagram may consist of parallel paths with the same durations. This is considered to be a problem deep down such diagram because project teams may find it diffuclt to chooose the most critical activities, hence create uncertainty on which path will be the critical path within the project. This may also cause the project teams to disagree as one team may hold one path to be critical and the another team may choose the other path to be the critical path.

No comments:

Post a Comment